Heat / Electric Usage Guide

Electricity supply procedure guide

  1. Complete application
    • 1. Electricity use application form: Please send it by direct mail, fax or refer homepage (www.cncityenergy.com)
      • - Electricity application form (Ⅰ): Contract power 5㎾ or less
      • - Electricity application form (Ⅱ): Contract power 6㎾ or more
    • 2. Application form : Download file from homepage
  2. Application receipt
    • 1. Visiting Reception : By the customer or By an electrician

      - Reception Office : 189 Kagahara Yuseong-gu, 3F Office of Collective Energy Office

    • 2. Fax: 042-336-5913 / Call after fax: 042-336-5600
  3. Field survey
    • 1. Measuring the distance from the underground manhole to the entrance

      - Check measurement result : confirmation of customer or field manager

  4. Payment of construction cost
    • 1. Billing cost : Send facillity contribution giro(Billing, email, fax)
    • 2. Payment of Facility Fees : Payment by bank transfer or giro payment (Including statement of cost calculation)
    • 3. Confirmation of payment of facillity contribution : Notification of deposit of designated financial institution
  5. Incoming construction
    • 1. Underground construction work
    • 2. Pre-use Inspection: Check whether the rated capacity of the cable is used and tmeasure the ground resistance.
  6. Install meter
    • 1. Dispensing and installation of meter : Installation of meter per unit and checking of operation condition
    • 2. Panel board check: Check whether rated circuit breaker or protective device is installed
  7. Equipment check transmission completion
    • 1. Extension Equipment Check : Use of certified product, ground resistance measurement

      - Ground resistance : Class 1 ground: less than 10Ω, Class 3 ground: less than 100Ω

    • 2. Transmission and Sealing