City gas Usage Guide

Contact List

Department
Location/Purpose Phone number Note
Dong-gu 042)336-5213 -
Jung-gu 042)336-5216 -
Seo-gu 042)336-5238 -
Yuseong-gu 042)336-5236 -
Daeduk-gu, Gyeryong-si 042)336-5215 -
Industrial 042)336-5211 -
Facilities allotted charges, Extension 042)336-5217 -
CNG 042)336-5232
042)336-5235
-

New supply guidance and procedures

Entire procedrues will take 2-3 months from the date of application.

  1. Check availability of supply

    Customers in the area where the supply pipe need newly install must contact with us for check availability.

    [Warning]

    Customer should be advised to contact us directly. If you proceed construction whitout our checking, every problems are your responsibility.

  2. Choose and contract plumbing company

    You must select a qualified plumbing company under the Construction Industry Basic Law to construct the plumbing in your site.

  3. Request supply (Partner Portal)

    You can request through cyber supplier portal or CNCITY energy.

  4. Payment of facility fee

    You must pay the facility contribution to dedicated account or a bill.

  5. In-house / branch piping construction

    Customer: It is necessary to plumbing through the constructor before the connect construction starts.

    Company: Connect construction is carried out through various licensing procedures such as road excavation.

  6. Pre safety check

    After plumbing, the contractor must submit inspection documents and inspected before the supply.

    If fail the safty inspection, you must correct flaws. Otherwise supply will never begin.

  7. Gas supply

    All construction and pre-supply safety check is passing you can request supply.

    Customers or plumbing contractor can not supply gas directly. If you request to supply gas to CNCITY energy Call Center (1666-0009), customer service center will supply gas after connection and inspection of combustion equipment.

Notes for
select plumbing contractors

There are first, second, third class of plumbing construction companies.

Qualification Example

  • - 01 : If the monthly usage is over 2,000m2 per month : Only first class can construct.
  • - 02 : In case of specific gas use facility (kindergarten, nursery, inn, religious facility, etc.) : Only first class can construct.
  • - 03 : In case of multi-unit(apartment building, villa, etc.) based on the building permission: Only first class can construct.(Addtional contrusct can be conducted by second class)
  1. When you select a contractor, it is advantageous to ask a few contractors for a quote, compare the cost and conditions, and then select the most suitable contractor.

  2. In the past, some construction companies were cheat people like supply available immediately even its not. Be sure to check the availability of supply so that you will not be affected as above.

  3. You must select qualified contractors according to the Basic Law of Construction Industry. Some contractors borrow a license from another company. Therefore, it is necessary to carefully check construction capability when selecting a contractor.

  4. You'd better write up the signed contracts with each other. Contract should contain about cost, duration of the collateral liability, the method of the collateral, the compensation for damages, and the total amount of the construction costs.

  5. Some contractor just disappear after deposit paid. Therefore, you alwasy caution for prevent financial loss when the contract is making.

  6. Depending on the situation, you able to receive a repair waranty from the contractor when it is completed.

Gas facility construction class type of work and qualification standard

Contact Us
Construction industry Business information Eligibility criteria Facilities Equipment
Gas Facilities Construction (Class 1)
  • - Class 2 and Class 3 business contents
  • - Installation / modification construction of city gas supply facility
  • - Installation / modification construction of facility of charge facility, collective supply facility, store of liquefied petroleum gas
  • - Installation / modification of specific gas use facilities of city gas facilities
  • - Installation / modification work of high-pressure gas piping
  • - At least one person with a Gas Industrial Engineer and at least five years of experience
  • - Civil Engineering Construction Law by Construction Technology Management Act
  • - One or more technical license holders of electrical welding, gas welding, special welding technicians according to National Qualifications Act
  • - A person who has worked for more than 5 years in gas related affairs and completed the training course for the construction of a gas facility builder by the Korea Gas Safety Corporation
Airtight test equipment and 9 kinds of others
Gas facility construction (Class 2)
  • - The work contents of the third class
  • - Installation / modification of specific gas use facilities of city gas facilities
  • - Repair work after the part where the supply pipe and the inner pipe are separated.
  • - Installation of fixed gas appliances to the piping and its subsidiary construction
  • - Installation / modification of liquefied petroleum gas with storage capacity less than 500Kg
  • - Installation and modification of liquefied petroleum gas sales facilities
  • - At least one person who is qualified as a Gas Craftsman and who has completed the training course for the construction of a gas facility builder by the Korea Gas Safety Corporation
  • - A person who has completed the training course for the General Facilities Safety Officer and construction worker by the Korea Gas Safety Corporation
  • - A person who has completed the training course for train the manager of the gas facilities workers by the Korea Gas Safety Corporation
Airtight test equipment and 3 kinds of others
Gas Facilities Construction (Class 3)
  • - The construction which is following items and construction amount is less than 10 million KRW
    1. Installation / modification of hot water boiler, water heater and related facilities in city gas use facilities
    2. Installation / modification of hot water boiler, water heater and related facilities in liquefied petroleum gas facilities
  • - A person who has completed the training for the hot water boiler installer or the training for hot water boiler construction manager in Korea Gas Safety Corporation
  • - Those who have completed the training to the Gas Facilities Construction Manager of the Korea Gas Safety Corporation
  • - As a person who has technical skill of first or second class of heating construction industry and completed training of hot water boiler construction manager and hot water boiler construction worker
Airtight test equipment and 3 kinds of others
위로가기